Hi All,
I have an issue with a delta from a standard extractor that is updating 4 datatargets in our system. Now, we are stopping the delta at the PSA for this extractor. I need to update 3 datatargets from the PSA before I update the 4th datatarget. This is because in the update rules for the 4th datatarget from this extractor, I am reading on of the 3 datatargets to update a field. Can this be done? If so, how do I automate this process in Process chains?
Please help.
Thanks,
Ashmith Roy
Message was edited by: Ashmith Roy
Hi,
This can be automated in process chain :
There is a std process type : "Read PSA and update Data Target".
Hope this helps you.
Guarav
*Assign pts if it helps**
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
80 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.