Skip to Content
0
Former Member
Oct 19, 2006 at 01:19 PM

Revoke status 'REL' for an activity

93 Views

Hi,

We use R/3 PS for managing projects. We use CJ20N to create and maintain project plans. If we release an activity (system status 'REL'), is there a way to revoke that? I looked at table TJ02T and there is one status defined as 'RELR' - Release rejected. Is this the one to be used? I would also like to know which transaction allows to do this. I have poked around in CJ20N but could not find a way to set this status.

Any info would be appreciated.

Thanks

Nirmal