Hi all

Is it not possible to have a warning if transaction posted with amount and Cost Center exceeded the Budget defined for Cost Center?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 04, 2017 at 02:22 PM

    Hi,

    I'm experienced in applying warning for cost center which budget is exceeded for SAP B1.

    My conclusion is not possible.

    So I used an alternate approach using approval procedure for cost center which budget is exceeded (it can be applied if one document consist of one cost center)

    or you can block it with SP_TransactionNotification.(it is not warning, but blocking)

    Hope this helps :)

    Regards,

    Rizki W

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 05, 2017 at 05:07 AM

    Thanks for the answer