Dear Sir,
I have below structure for Variant-
Level 1-KMAT
Level 2-KMAT
Level 3-KMAT
Level 4-KMAT
Level 4-ROH and HALB
All variant are configured and select in sales order properly.
at time of MRP run only level 1 material are exploded, system not go up to level 4.
We have maintain the strategy 25 in MRP view for all KMAT level.
Please help to sort out this issue.
Regards,
Sumit Yeole
Please check what BOM application assigned to each level in configuration profile as well as what BOM usage maintained for all these BOM's. Probably the second level BOM usage is not matching BOM application maintained and thats the reason BOM explosion not happening.
you can also go through below notes it may also help.
210210BOM explosion:Conf.material with phantom assemblies42511BOM: Error in low-level code assignment39032No BOM explosion with production versionThanks
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.