on 10-17-2006 5:44 PM
Hi!.
When I confirm an internal activity on the project system, actual cost value seems to be duplicated. Customizing procedure has been properly performed. Activity Type Price is set to 22 / hour and after confirming one hour, actual cost value appears as 44 .
Does anybody have a clue why this is happening?.
Thanks in advance!
Dear Raul,
The Controlling Area currency is different of the Company currency?
The Planning layout in CO defines where currency the price is planned.
In PS the reports standards are in controlling area currency.
Please verifies and send me the result from this error.
Best Regards
Elza