on 04-03-2017 1:30 PM
Dear Experts,
I have an issue where for a production order the basic finish date for the order is getting scheduled on a non working day on sunday. scheduling type for the order is Backwards. when the user has scheduled the order it has been scheduled on sunday say 09.04.2017 as basic finish date and also the requirement date for the reservation components is set on 09.04.2017.
Factory calendar for the plant has saturday and sunday as holiday without any special rules. Control key doesn't have the indicator "Scheduling". I checked the customizations but couldnt find the issue. Please provide your suggestions
Regards,
J.Balakrishnan
is there a different factory calendar assigned in the work center? That would take precedence over the factory calendar assigned to the plant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.