Skip to Content
0

Production order gets scheduled on non working days

Apr 03, 2017 at 12:30 PM

56

avatar image
Former Member

Dear Experts,

I have an issue where for a production order the basic finish date for the order is getting scheduled on a non working day on sunday. scheduling type for the order is Backwards. when the user has scheduled the order it has been scheduled on sunday say 09.04.2017 as basic finish date and also the requirement date for the reservation components is set on 09.04.2017.

Factory calendar for the plant has saturday and sunday as holiday without any special rules. Control key doesn't have the indicator "Scheduling". I checked the customizations but couldnt find the issue. Please provide your suggestions

Regards,

J.Balakrishnan

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

DOC11 Apr 21, 2017 at 04:19 PM
0

is there a different factory calendar assigned in the work center? That would take precedence over the factory calendar assigned to the plant