on 04-03-2017 10:23 AM
Hi All,
I am using task TS20000159 for PR Agent Determination and getting approvers from User Exit. All is fine. I want to use Deadline Monitoring and I am aware how to achieve it. Questions
1) Shall I use the same task for Deadline Monitoring. If Yes, where to write logic for the 2nd level Approvers.
2) If not the same task, how shall I approach!!
hi,
You have to maintain deadline modelled monitoring in the same task, and create another Task for 2nd level approvers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.