Hi,
I don't know how to transport the configuration made in ISA development system to ISA productive system.
I need to set up the productive system but I don't know if ISA configuration could be transport or what's the best procedure for it (copy some files, transport with some tool, made it again manually in productive system...)
Could anyone help me please?
Kind Regards
Javier
Javier
If you are using SAP CRM 5, then Transport of Objects is done with the help of NWDI.
Go the Transport view and release your corresponding Transport !!!
Thanks
Jack
<b>Allot points if my post helps !!!!</b>
dear Javier,
i´d been working on a 5.0 migration recently, and we created a project for the "old" version in JDI (aka. eclipse) and imported our project (or Software-component as SAP calls it)product there. Then it was available in the DTR and could be deployed to the there known systems. a speciality were the system connections,
that were all configured in the development environment,
(as d...,t...,p...), and have simply been manually switched after transport to the relevant environment.
hth, bye
Jürgen
Add a comment