Hi,

I would like to know where we can find at table level a specific MRP Element- Requirements displayed in MD04 is fulfilled by a specific order proposal.

Lets say we have OrderRes1, OrderRes2, OrderRes3 and corresponding to this, we will have Procurement Proposals- ProdOrder1, ProdOrder2 and PlannedOrder3.

Can we able to see the link between Production Order 1 and OrderRes2 or OrderRes1 at table level , so that we can say that a specific requirement is met by a specific Procurement proposal.

Thanks in advance for your suggestions.

Accepted Solutions (0)

Answers (2)

Answers (2)

solomon_macwan
Active Contributor
0 Kudos

Hi Aditya,

Pass AUFNR(Order no) in AFKO table - you will get reservation no (RSNUM).

pass RSNUM into RESB table, you will get all the reservations for that order.

regards,

Solomon

former_member184595
Active Participant
0 Kudos

Hi,

I would like to know where we can find at table level a specific MRP Element- Requirements displayed in MD04 is fulfilled by a specific order proposal.

Lets say we have OrderRes1, OrderRes2, OrderRes3 and corresponding to this, we will have Procurement Proposals- ProdOrder1, ProdOrder2 and PlannedOrder3.

Can we able to see the link between Production Order 1 and OrderRes2 or OrderRes1 at table level , so that we can say that a specific requirement is met by a specific Procurement proposal.

Thanks in advance for your suggestions.