Why can configurable materials not be used in service orders?

Former Member
0 Kudos

I receive message IW292 when trying to use a configurable material on service orders. I am trying to understand the reason why this is not supported.

Thanks

Kimbie

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

We are on 6.0, EHP6

peter_atkin
Active Contributor
0 Kudos

That's interesting Santosh - I've not seen this before...

Do you have any document references??

PeteA

Former Member
0 Kudos

hi,

May I know the version which you are using ?

SAP has already released some Support packs to use this functionality from ECC 6 onwards

Former Member
0 Kudos

Hi Pete

We are going to be using configurable materials on PS projects, and I'm regression testing as some of these materials we also use is CS orders (yes on the components tab). I receive message IW292. Just trying to understand the logic as to why they cannot be used.

Tks

Kimbie

peter_atkin
Active Contributor
0 Kudos

Kimbie,

I'm assuming you get this error when entering the configurable material in the Components tab??

If so, then the PM/CS orders cannot handle these types of material.

What are you trying to achieve?

PeteA