Why can configurable materials not be used in service orders?

I receive message IW292 when trying to use a configurable material on service orders. I am trying to understand the reason why this is not supported.

Thanks

Kimbie

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Apr 03, 2017 at 11:00 AM

    Kimbie,

    I'm assuming you get this error when entering the configurable material in the Components tab??

    If so, then the PM/CS orders cannot handle these types of material.

    What are you trying to achieve?

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 03, 2017 at 01:54 PM

    Hi Pete

    We are going to be using configurable materials on PS projects, and I'm regression testing as some of these materials we also use is CS orders (yes on the components tab). I receive message IW292. Just trying to understand the logic as to why they cannot be used.

    Tks

    Kimbie

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 04, 2017 at 05:52 AM

    hi,

    May I know the version which you are using ?

    SAP has already released some Support packs to use this functionality from ECC 6 onwards

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 04, 2017 at 09:02 AM

    That's interesting Santosh - I've not seen this before...

    Do you have any document references??

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 04, 2017 at 06:40 PM

    We are on 6.0, EHP6