Why can configurable materials not be used in service orders?

Mar 31, 2017 at 07:52 PM

111

avatar image
Former Member

I receive message IW292 when trying to use a configurable material on service orders. I am trying to understand the reason why this is not supported.

Thanks

Kimbie

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

5 Answers

Peter Atkin Apr 03, 2017 at 11:00 AM
0

Kimbie,

I'm assuming you get this error when entering the configurable material in the Components tab??

If so, then the PM/CS orders cannot handle these types of material.

What are you trying to achieve?

PeteA

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Apr 03, 2017 at 01:54 PM
0

Hi Pete

We are going to be using configurable materials on PS projects, and I'm regression testing as some of these materials we also use is CS orders (yes on the components tab). I receive message IW292. Just trying to understand the logic as to why they cannot be used.

Tks

Kimbie

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Apr 04, 2017 at 05:52 AM
0

hi,

May I know the version which you are using ?

SAP has already released some Support packs to use this functionality from ECC 6 onwards

Share
10 |10000 characters needed characters left characters exceeded
Peter Atkin Apr 04, 2017 at 09:02 AM
0

That's interesting Santosh - I've not seen this before...

Do you have any document references??

PeteA

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Apr 04, 2017 at 06:40 PM
0

We are on 6.0, EHP6

Share