Problem in Assembly Processing in Project System(WBS is required in SO)

I have done SAP setting according to the link below.

https://wiki.scn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems

When I create SO, WBS element is required. If I input the WBS I created, Error Msg CN044 is shown.

How can I solve this problem?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Mar 30, 2017 at 05:30 PM

    Hi Wan,

    Did u assign material to standard network in cn08. This scenario should automatically create WBS. If possible please paste the screen shots of the config you have.

    Thanking you

    Vengaiah

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 03, 2017 at 08:22 AM

    Hi Vengaiah

    Thank u for your help.

    I know why I need to input WBS when SO is created.

    When I defined fields selection for networks, I have set WBSE as required.

    Thank you.

    Wan

    Add comment