Hi SDNrs (it was good to meet some of you in Vegas)
We recently applied patch 9 to our BW2004s system and it seems since then we are unable to activate data loads in various DSOs. See the following errors:
Resource error. No batch process available. Process terminated
Time limit exceeded. No return of the split processes
We have tried various permutations i.e. removing checks on automatic activation, condensing etc - but no luck. Have any of you had this problem and if so any ideas as to how to resolve?
Thanks
Shin