MRP :Re-order not generating proposal

jaheer_hussain
Active Contributor
0 Kudos

Hi,

MRP reorder point is not generating any proposal for my material .my material type is ROH. I saw many threads in the SDN,still it is NOT helping me to solve my problem.

can you please help to solve this problem by giving some tips?

1.gif

And my stock for this material is zero.

MD02 screen:2.gif

MD04 screen:

3.gif

Accepted Solutions (0)

Answers (8)

Answers (8)

jaheer_hussain
Active Contributor
0 Kudos

Thank you Mr.Jurgen. Problem solved.

JL23
Active Contributor
0 Kudos

MRP run always takes the number range from OMI2 transaction.

jaheer_hussain
Active Contributor
0 Kudos

I checked this 'this Materials with New Exceptions' in MD06,there is an error message "Number range for object BANF does not exist" and also please see screen.

4.jpg

But I have number range for PR.5.jpg

jaheer_hussain
Active Contributor
0 Kudos

Not able to check 'this Materials with New Exceptions'. I ran it foreground.

please see the screen.

3.jpg

Regards,

JL23
Active Contributor
0 Kudos

I have in this screen a box to show the results before saving, is this box activated when you execute it?

JL23
Active Contributor
0 Kudos

Your second screenshot from your initial post says

"Materials with new exceptions"

Had you checked these exceptions from the menu "EDIT" (or Shift+F8) if you ran it in foreground?

jaheer_hussain
Active Contributor
0 Kudos

In my planning ,I have given planning date 31.03.2017,that is why it is not working ????????

JL23
Active Contributor
0 Kudos

you can easily proof this yourself by executing it with todays date.

jaheer_hussain
Active Contributor
0 Kudos

Hi Jurgen,

I have planning file also as below.please see also MD02 screen also.

1.jpg

2.jpg

With Regards,

JL23
Active Contributor
0 Kudos

If you had seen many discussions then I wonder that you did not stumble over an advice to check if you have a planning file entry in MD21