HI Gurus ,

We are working towards an enhancement where we need to send the planned order to the 3rd part tool (Scheduling Optimizer) & then we need to upload the modified Basic Dates & and Basic time to the SAP for planned order .

We are using the BAPI to upload the planned order dates to the SAP .

But when we are converting the planned order to the process order then system is picking the basic dates but not the basic times into the production order . We used both the option " Backward/Forward scheduling" & "Backward scheduling with time" but still it is taking the time 00:00 & 24:00 .

As I know this kind of timing will control based on the In house production time in the material master (Work Scheduling View) . Our requirement is to copy the exact Basic Date & time into the process order while conversion

Do we need to use any kind of enhancement in process order to get the basic dates & time from PLAF table to copy the same into the process order during the conversion ?

Or is that any standard way to achieve this ?

Is this kind of enhancement will be safe?

How we control this when we get the scheduled planned order from the APO ?

Thanks,

Regards,

Aman