Delete planned costs in Production order

Mar 29, 2017 at 02:32 PM

82

avatar image

Hi experts,

Is it possible to delete planned costs from an active production order?

Best regards

Klaus

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Solomon Macwan Mar 30, 2017 at 05:11 AM
0

Hi Klaus,

Why do you want to delete it.

If you do not want to cost than simply mark as do not cost in material master.

Regards,

Solomon

Share
10 |10000 characters needed characters left characters exceeded
Klaus Gross Mar 30, 2017 at 02:42 PM
0

Hi Solomon,

It is a make to order scenario. We have recently activated the planned costs for those order type. Now our planned costs in the Sales order result analysis are too high.

Best regards

Klaus

Share
10 |10000 characters needed characters left characters exceeded
sap sap Mar 31, 2017 at 08:49 AM
0

HI klaus,

Can you please explain your scenario in detail.

Regards,

mahesh.

Share
10 |10000 characters needed characters left characters exceeded
Klaus Gross Apr 05, 2017 at 12:18 PM
0

Hi Makesh,

currently we are doing the planned costs on sales order item level. Unfortunately a user was calculating the planned costs of the whole production order net of such a sales order.

Now the result analysis of the sales order is including the planned costs of the sales order + all planned costs of the production orders. In theorie one solution would be to delete / initialize the planned costs of the prodcution order, if possible?

Best regards

Klaus

Share