In CK13N Tcode can we have by default system select the Costing Status as FR

Mar 28, 2017 at 09:12 PM

200

avatar image
Former Member

When we are in T code CK13N and input the details such as Material No, Plant, Costing Variant, Costing version, Valid on details --- System provides an output of the cost estimate of the material based on a Costing Status KA (Costed without errors).

If I would like to see the costing status as FR ( Released Without Errors ) by default from CK13N, what are the options that are available in SAP.

Can we make this change to FR, and so going forward system will always show for a material the released cost estimate as per the latest date or provide an option to choose the KF status dates.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Nishan Dev Singh Mar 28, 2017 at 09:52 PM
0

Hi Purna,

I would not recommend that, as all this message status has different results, here for example -

Status - KA The cost estimate has the status KA (costed without errors). The cost estimate has therefore yet to be marked or released.
Status - VO The cost estimate has the status VO (marked without errors). Costing has been carried out, and the cost estimate has been marked but not released.
Status - KF. The cost estimate has the status KF (costed with errors). Status - FR. If a standard cost estimate has already been released (status FR ), it cannot be costed, marked or released again.

Thanks,
Nishan Dev

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Mar 28, 2017 at 10:41 PM
0

Thank you Nishan Dev.

I understand the explanation shared on Status for a cost estimate.

Would like to know, in case we need the feature what I shared in the discussion it would help me.

Share
10 |10000 characters needed characters left characters exceeded
Nishan Dev Singh Mar 28, 2017 at 11:34 PM
0

Hi Purna,

SAP will not allow you to change unless this is an urgent repairs in object belonging to SAP, System will give a warning message, with namespace, and still if you want to proceed, it will take you to language conversion from DE to EN.

Please give a try - SE91, message class - CK and give the message number you are getting while changing it.

I would not recommend to any of my clients to do this, rather I will copy this message and create a Z message and allow to make a change there but not in standard message control.

Thanks,
Nishan Dev

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Apr 01, 2017 at 05:38 PM
0

Hi Purna,

I think you can't display FR Status in CK13N but you can create a SAP query report to display materials with this status and with the details in CK13N and you can make it with these tables KEKO, CKIS and CRTX.

hope this will help you.

thanks,

Ahmed Nassar