Hi all,
A delta data load to the cubes 0PUR_C01 and 0PUR_C02 has failed today. There was an error in the Scheduled line date. The date was entered as 09/29/0606 instead of 09/29/2006.
To edit the record, I deleted the data in all the data targets. I edited the record and saved it in PSA. From PSA, I scheduled the reload using Update immediately.
The loads to the cubes failed giving me the same error. So this is what I did. I edited the record, saved it in PSA. I forced the QM status to green and then scheduled the load.
I wanted to know if I have done it right or wrong. Your inputs and advice are highly appreciated.
I look forward to listening from the experts.
Regards,
S.P