Mar 28, 2017 at 07:50 PM

Incorrect Production Version in S4 after Change of Source of Supply/PDS in PPDS

148 Views

Experts,

We are using S4 1610 version. When we switch SOS/PDS in PPDS, via the Planning board the following happens:

  • Planned Orders & Process Orders adopt the new PDS in PPDS, however, the new PV doesn't get reflected in S4.

Planned Orders are created from S4 & SOS/PDS change is triggered from Planning Board. Conversion of Planned Orders is also triggered from PPDS.

Any clues?