Incorrect Production Version in S4 after Change of Source of Supply/PDS in PPDS

andy_yeri
Contributor
0 Kudos

Experts,

We are using S4 1610 version. When we switch SOS/PDS in PPDS, via the Planning board the following happens:

  • Planned Orders & Process Orders adopt the new PDS in PPDS, however, the new PV doesn't get reflected in S4.

Planned Orders are created from S4 & SOS/PDS change is triggered from Planning Board. Conversion of Planned Orders is also triggered from PPDS.

Any clues?

Accepted Solutions (0)

Answers (2)

Answers (2)

andy_yeri
Contributor

#2403565. Hope it helps!

andy_yeri
Contributor

This was another programming bug b/w S4 & PPDS. A note helped us fix this.

0 Kudos

Hi Andy,

Which note solved it? Please, share it and close the thread, as someone else facing the same issue may be able to find solution here. Thanks.