fix bom quantity during creation production order

Mar 28, 2017 at 12:07 PM

82

avatar image

hi gurus

i have a question in my mind that, is it possible that during creation production order ( co01 ) , how i can fix a component quantity which in BOM.

when i create production order with routing and actuall plan consumed components than system do not allow me excess quantity of plan components.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Mar 28, 2017 at 01:36 PM
0

Hello

If I understood your question correctly, you don't want to allow the consumption above the planned quantity. If this is the case, this is not possible in standard and you must use BAdI WORKORDER_GOODSMVT to implement a check.


Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded

yes dear. you r well understand my question. but why this is not possible in standard. end user always consume excess quantity as i feed planned quantity in production order.

please find out solution of this error.