Hi PM Experts,

My client wanted to close PM orders under some cost centers.

There are some open POs against the Cost Centers.

What is the relationship with these cost centers and Open P.O.’s if we want to close the PM Orders directly ?

Please provide your thoughts ...

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 29, 2017 at 06:43 AM

    If ther PO items are "accout assigned" to cost centres, then there will be no relationship to the PM/CS orders.

    Therfore you will be alble to close the PM/CS orders.