Cost Centers and Open POs in WO

Former Member
0 Kudos

Hi PM Experts,

My client wanted to close PM orders under some cost centers.

There are some open POs against the Cost Centers.

What is the relationship with these cost centers and Open P.O.’s if we want to close the PM Orders directly ?

Please provide your thoughts ...

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

If ther PO items are "accout assigned" to cost centres, then there will be no relationship to the PM/CS orders.

Therfore you will be alble to close the PM/CS orders.

PeteA