SOP-RCCP-Rough cut capacity calculation

Hi Gurus,

Need your help to understand the calculation of rough cut capacity during SOP.

Fig1 - shows Rough cut planning profile. For 6000 Kg, 30 Days needed. Resource available for 240 Hrs a month (8 Hrs per day, off on Sat and Sun).

Fig2 - SOP screen showing capacity situation. Avlbl Hrs = 160, which seems correct as pr resource settings.

For Apr 2017, For qty 3500, I would expect capacity reqmt as 3500/6000*240 = 140 Hrs.

However, it is showing 1760 Hrs. How this calculation is done?

I have checked some threads showing calculation, but those do not provide exact insight into my problem.

Appreciate your quick response please:)

rccp-calculation.jpg

rccp-profile.jpg (100.4 kB)