Change of material master during transfer between SRM and R/3

Hi,

I have a question for modifying material master data between R/3 and SRM.

I would like to know if it is possible to change the material number during the transfer. The reason is:

I have 2 R/3 backends and 1 SRM system. The material codes in the 2 R/3 systems are different but some materials having different numbers in R/3 are referring to the same material. I want to see such materials with the same material number. Is it possible to do this with Middleware plus some interruption in between? The "translation" should be bi-directional.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 22, 2006 at 05:55 AM

    Hi,

    While replicating the materials from the 2 backends into the SRM system,they will be replicated under different Hierarchies in SRM.

    What you can do is after replicating the such materials(those having diffreent material codes but referrig to the same material),you can modify the Product Search in SRM for displaying such kind of materials.

    BR,

    Disha.

    Pls reward points for helpful answers.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.