Kindly help me on the following:-

My project is closed but some goods are to be recd for PO which was raised before closing .

But I don't want the financial impact on my project , I can allow the cost to be posted to any cost centre but not to WBS.

Second similar thing I want to ensure for any other finacial transaction.

What shud I do, set some user status, TECO or else.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2007 at 08:00 PM

    Hi,

    Change the ‘PO’ account assignment ‘WBS’ to ‘Cost Centre’ and do the goods posting. Make sure that if reservation created from ‘WBS’- Network than you need to close the PO and create new with reference to cost centre.

    Enjoy SAP………

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.