How to reduce commitments in Internal order, once it is assigned in a purchase order ?

0 Kudos

Hi,

This is a new incident we received from our clients,

Say our Purchase order is made of Rs 100, MIGO was done of Rs 100.

But then the Vendor sends a Invoice of Rs 90/-

Now the issue is, Internal order is assigned to a purchase order and in KO22 we can see the assigned value as Rs. 100.

But since the vendor has only charged Rs 90/-, the internal order is booking an additional Rs 10/- which should not be the case.

The budget maintained for this order is Rs. 1000.

Is there any way that we can change the assigned field in KO22 for an Internal order and decrease it to 90 ?

iklovski
Active Contributor
0 Kudos

Hi,

Is IR marked as final invoice?

Regards,

Eli

0 Kudos

Hi,

Yes, this is the final invoice from the Vendor.

Regards,

Gavin Monteiro.

Accepted Solutions (1)

Accepted Solutions (1)

iklovski
Active Contributor
0 Kudos

Hi,

Please, check OSS note 733733 - No commitment reduction despite final invoice indicator.

Regards,

Eli

Answers (1)

Answers (1)

nishan_dev
Active Contributor
0 Kudos

Hi Gavin,

Yes you can change the budget number in KO22 to 90 without any issue, if you want to match the reports numbers, are you getting any error during the change?

Thanks,
Nishan Dev