Hello,

My client's requirement is to price the articles on Vendor/Article/UOM but the case is as below illustrated with screen shots:

1- Prices of UOMs defined as below

2- when creating purchase order with PC and CAR, price is coming right

3- when changing the UOM in the 2nd line item as seen below, the price is not updated

My Questions is: Is there any way that the price is changed automatically without have to press on the update button

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Mar 27, 2017 at 09:15 AM

    why should it be changed? The price has its own unit and this has not changed:

    did you already try to click the update button, I doubt that you get a different result using the button if you did not include the unit itself as key in your price conditions.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 27, 2017 at 10:12 AM

    Hello Jurgen,

    Thanks for your reply.

    I have changed the order unit and the price has not been updated.

    uom-pricing-reply.png

    I know that it will not be updated unless I click on the update button, but my customer wants the price to be updated automatically without having to do this step (clicking on the update button) because customer is afraid of user entry error.

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 27, 2017 at 10:48 AM

    I think your client has to get used to the SAP standard design.

    I actually think that you get less errors and user entry errors with a consistent concept. e.g. you should look for the reason why the material is defaulted with CAR as unit and why this needs to be changed to PC. With the right masterdata settings such changes in the PO should not be needed at all.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 27, 2017 at 12:55 PM

    check material master addtional field what has been maintained and also check PIR for variable unit of measure.

    You have to maintain the price then it will take it according to unit

    This is the way, you can update the price

    R

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 27, 2017 at 01:04 PM

    I agree with Jurgen , but still if you want you can automate it by a simple batch job that identifies POs that are affected by price changes and then carry out a mass repricing action by using BDC recording. Not a good solution but can do the job