Hi Experts,

Our clients requirement is to consume the budget only at the stage of GR and at the time of IR, the budget should not be consumed. To change it in OFUP, please guide me with the pre requisies to be followed and the impact if it has to be changed during mid of the year.

We use ECC 6 Ehp 8

Thanks

Manoj M

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 27, 2017 at 07:07 AM

    Hi,

    Changing from GR/IR to IR should be easy from procedural perspective. I wouldn't anticipate any problems with this.