on 03-26-2017 3:38 PM
Hello team,
We have a requirement that some transnational data will be coming on to IBP through manual excel sheets by-weekly. And to not make it complex, we are not integrating with that legacy system and settling with excel sheets.
Question: Do we to configure this data integration upload job in HCI ?
Or is there a way to be done in IBP itself ?
Looking forward for some knowledge sharing
Hi Venkat,
Data transfer scheduling as a batch job is possible from HCI and IBP.
Option 1: HCI
You need to work with HCI consultant to schedule batch job.
Option 2: IBP
Go to "Application Job Templates" application and create new Job template using "Data Integration Using SAP HCI". In this step also you need help from HCI consultant to provide agent, task details informatio.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.