hai experts

I have around 12 workcenters, and in that every shift only 5 to 6 workcenters are working but the labours are not fixed on that work center and around 15 labors are working in shift and these labours are varying too, so how to create the formula in workcenter and how to give everyday labour quantity in workcenter, as company needs both machine and labour costs..

thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 27, 2017 at 12:50 PM

    Hi Abdul,

    I believe that all the 12 work centers are doing the same job at a time. and you do not need to maintain each work center separately in system. You can create one work center as LABOUR and its capacity individual capacity as 12. You can also maintain the capacity utilization as 50% in capacity tab in work center. You can assign the the labor to the w/c in general tab and in capacity tab as HRMS. so that you can

    Now for calculating the cost - In standard value key, you maintiain the std value as Labor, Maintain the activity type and cost for Labor in KP26.

    So whenever you confirm the order you maintain how many labors were used. lets say 14 Labors where used. than it will calculate the labor cost based on the kp26.

    Hope this is helpful.

    regards,

    Solomon