on 03-24-2017 10:44 AM
Hello,
Please is there any BADI/EXIT that influence MRP results when it creates schedule lines ? Or modify schedule lines for a scheduling agreement after the MRP run.
I would like to regroup schedule lines generated for a scheduling agreement according to my own logic. For example :
- Requirement
dependent requirement : qty 100 - date 24/03/2017 at 10:00
dependent requirement : qty 050 - date 24/03/2017 at 11:00
dependent requirement : qty 050 - date 24/03/2017 at 15:00
- Standard result
Schedule line = qty 200 - date 24/03/2017
- Required result
Schedule line = qty 150 - date 24/03/2017 at 12:00
Schedule line = qty 050 - date 24/03/2017 at 15:00
Thank you.
Hello,
I am answering this for folks seeking for a way to achieve this :
- Not possible, neither BADI nor User exit can achieve this through ERP. AP
Please check this note :
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.