Mainteannce plan not generating work orders once previous order is closed

Hi all

In Maintenance plan we have put completion requirement required checked.But when teco is completed for work orders it is not scheduling next work order autamatically

We have to go and remove teco and do teco again.Only then it is generating subsequent work from maintenance plan

Can you kindly let us know if any one had faced similar issue

regards

krish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Mar 24, 2017 at 09:06 AM

    Swet,

    I'm assuming that you are using IP30 for your auto-creation of orders from maintenance plans?

    There are quite a few OSS Notes relating to maintenance plans and completion confirmation. Take a look at these..

    If you have any developments in the order, then deactivate these and re-test.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 24, 2017 at 09:33 AM

    Thank you. Let me check fi any oss notes would solve the problem.But is there any thing else needs to be check as i think it happens only for few plants

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 24, 2017 at 01:33 PM

    Check your IP30 logs to see if that gives any ideas.