Class BATCH_CLASS is currently locked by user 400

Hello Experts,

we have scheduled background job for RIMODINI to transfer PDS from ERP to APO but job is getting cancelled and throwing error " Class BATCH_CLASS locked by user 400".

Please help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 05, 2017 at 11:22 PM

    Hi Mukesh,

    Does the queue get stuck in APO inbound with this error or is the lock on ECC side? Are you able to enter change mode for this class in CL02 transaction? Do you see any relevant locks in SM12?

    Regards,
    Tiago

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 07 at 10:22 AM

    Hi Mukesh,

    Did you solve this issue? I have same problem

    Regards,

    Matt