Update planned quantity in Production Order from second task

Hello All,

I have the following scenario:

- Products:

Input Product A - 1 UN

Input Product B - 1 UN

Output Product C - 1 UN

- Tasks:

Input Products A and B enter the first task

They suffer a transformation in a second task

Output C Product is reached in the last tasks.

My goal is to have the planned quantity of output product C in the second and third tasks matching the confirmed quantity in the previous task.

So, if I plan to produce 10 UN of C and at the end of task number one 8 UN are confirmed and 2 UN are scrapped I consume 10 UN of A and B.

But I want to have 8 UN in the planned quantity of task 2 and the matching quantity of the input products A and B.

Right now I keep having the same planned quantity for the output product in the second and third taks.

Can you tell me how this can be done?

Thank you.

Best regards,
Pedro Mariano

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Apr 20, 2017 at 11:37 AM

    Dear Pedro,

    The quantity planned for production will not change no matter how many tasks you have or how much quantity you have confirmed/scrapped. The value of planned quantity is updated to the tasks through production order. Even if you have scrapped most of the items the quantity that was planned for production will always be same and will not change.

    You will always have the visibility of how much quanitty you have confirmed in the tasks along with the planned quantity.

    Regards,

    Anand

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 08, 2017 at 08:42 PM

    Dear Anand,

    Thank you for your reply.

    Best regards,

    Pedro Mariano