on 03-22-2017 6:08 PM
Dear PP/DS Group
1. In APO PP/DS Planned Order created for Source of Supply with PDS 1 .
2. In ECC MD13 Planned Order reflected correctly.with PV1 (Prod.Version)
3. In APO PP/DS Planned Order changed for Source of Supply with PDS 2
4. In ECC MD13 Planned Order not reflected .with PV2 (Prod.Version),
it remains same as PV1.
What could be the reason?
All CIF settings are rightly in place.
Appreciate the assistance.
Poongunran
Hi S,
In /SAPAPO/CCR, are the differences in content detected? Also, does the change date/time of the Planned Order on ECC reflect the date time you switched the Source of Supply in APO? It's possible the queue got stuck in the inbound of ECC and did not get processed, in which case most likely this will be shown in CCR so you can reconciliate the order.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.