From ekko, I want to know if a ebeln is a PO, RFQ, Scheduling agreement or contract. I think BSTYP is the only field which I should check. Is n't it? OR are there any other criteria?
Please let me know your opinions.
Thanks.
Yes BSTYP is the only field that you need to check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U can Identify the Ebeln with help of BSTYP type field.
IF BSTYP = A.
Ebeln is Request for quotation
IF BSTYP = F.
Ebeln is Purchase order
IF BSTYP = K.
Ebeln is Contract
IF BSTYP = L.
Ebeln is Scheduling agreement
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yep. That is the way to go.
Here are the following possible values for field BSTYP:
A Request for Quotation
F Purchase Order
K Contract
L Scheduling Agreement
So that is all you need.
Leonardo De Araujo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.