Skip to Content
0
Former Member
Aug 30, 2006 at 08:03 PM

PO change tracking and output

156 Views

Hello,

I am working on Purchase Order changes.

I have 2 problems to address:

1)after I output a PO, I am changing the PO, for example, the net price, I expect the system to release another output with the changes.

I have set up NEU with the operation 2 in Fine tune control for POs and net price is one of the " print relevant changes".

But still the PO is not output with the changes.

2) My requirement is to use version numbers to track the PO changes. When I am making changes in the PO,a new version number is assigned only when I "complete" the previous version. "Complete" is a checkbox in the Po header. I have to manually check this box. I would expect the system to automatically assign a new revision number depending on the print relevant changes changes made.

I would appreciate any thoughts on these two issues.

best regards,

Srinivas