Hello Guys

Employee got loan and repaying and in March2017 he requested HR team not to deduct lone and to deduct from April2017. Please let me know to make it happen? By changing IT0045 without creating any duplicate or multiple records

Regards

SK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

7 Answers

  • avatar image
    Former Member
    Mar 21, 2017 at 11:19 AM

    Dear SK,

    Kindly change the end of specific loan also make repayment as zero and create new copy with remaining amount.

    Regards

    Jazib

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 23, 2017 at 06:58 AM

    Hello Team

    Any Update on this please

    Regards

    SK

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 28, 2017 at 10:52 AM

    Hi SK,

    T-code: PA30--> Put employee ID -->Select Infotype 0045 (Loan)--> click on Overview--> Select Loan--> Copy

    System asking new start date (in your case April 2017) and save.

    Please make a test case in sandbox or development and do the above activity, after satisfied with result, apply in production.

    Enjoy the day

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 28, 2017 at 11:32 AM

    Hello SK,

    Copy the loan record and maintain start date as 01.03.2017. In the conditions tab, maintain repayment start as 01.04.2017 and then SAVE. You may notice that new record is created with sequence number.

    Rgrds,

    Sravan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 29, 2017 at 12:09 PM

    Hello Both

    In this case what happens to existing loan record (if i copy and create new Loan types)?

    Will it be correct solution?

    Regards

    SK

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 10, 2017 at 12:02 PM

    Hi SK,

    According to my understanding this is the one of the way

    Yes this is the right way.

    Enjoy the day!

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 11, 2017 at 07:19 AM

    Dear SK,

    Follow the following process,

    Go to PA30 and IT45 and subtype and press overview button. After that select the relevant loan and press copy button and give month start date and end date and in repayment installment remove the amount.

    Now press save button. system will prompt you that record will be saved in the splits, least bother that warning and save the record.

    Now after saving if you see the IT0045 for this particular loan type you have 3 records coming.

    1. From start date till one month before

    2. Current month which you skipped

    3. New month mean next month.

    Now select the New month record and press change button and go to payment tab, there is one button for repayment date calculation (small yellow button), press that button and it will automatically change the last date of the record.

    Now check the payroll, system will not generate the /LRP for skipped month.

    Regards,

    Uzair