GATP in SCM 5.0

Gurus,

I work as an APO GATP consultant and would like to know whether the following is available in SCM 5.0

1. Customer wants to group all the items in a sales order for a single source plant after a Rules based ATP check. This is a sales order optimization issue so that a single source plant cant be selected for all the items.

2. When making a decission on single plant sourcing like above, how do we take care of the cost factors and lead time . The cost factors are transportation costs which vary from plant to plant.

3.Can a Multi-level ATP be used without PPDS. Customer wants to check BOM items only fo inventory.

4. How do I hard allocate a batch in a sales order (batch managed material) so that other orders should not pick the batch during back order re-scheduling

I appreciate all your inputs.

regards.

shan

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 25, 2006 at 11:07 AM

    Hi Shan,

    I will answer the first 2 questions.

    1. Yes this is possible. All you need to do is create rules with Location determination so that same plant is determined for all the line items. Then configure the rule determination based upon some independent entity (Sold-to-party) for example.

    2. The lead time will be taken care of by the Scheduling information that you will need to maintain. That is you will have to create condition records which give the lead times for each plant. They will be automatically picked up when a sales order is created. The costs will also be taken care of by the TP/VS module. When you create plants , create lanes, maintain the costs needed.

    Hope this helps.

    Cheers,

    Ankur

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 22, 2006 at 02:18 PM

    Ankur,

    Thanks for your inputs. Let me know if you get any answers for other questions.

    You have any experience in product allocation in APO ?

    regards,

    shan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Ankur,

      1. Can I use different units of measure on planning book? Because when u configure planning area, it accepts only one UOM. But if the user wants to put different UOM on planning book, how he will do it?

      2. I want to consume product allocation fully w/o giving partial confirmation. For eg: if I have 50 availavle in this week on each of the day , and if I order 100, I should not get any confirmation in this week. I should look for 100.

      regards,

      shan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.