Skip to Content
0

Issue with CJ88 postings in SAP

Mar 20, 2017 at 03:51 AM

56

avatar image

Settlement posted using CJ88,randomly some documents translation is taking previous year.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Vengaiah Chowdary Pachava Chinna Mar 20, 2017 at 04:24 AM
0

Hi Satish,

Above documents are not Cj88 postings. CJ88 postings will have Posting date as last day of the month irrespsctive day you have run the settlements. So can please recheck the origin of the postings.

Thanking You

Vengaiah

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Vengaiah,

Yes, your are correct using CJ88 whenever in a month we do settlement it will post to last day of the month.Currently that is happening for other cases, randomly for some the translation date is picking last year or before year.

Please see the below 2 posted documents,posting date is 3/11/2015 and translation date for one is posted to 3/31/2015 which is correct and other is 3/31/2014.Documents are posted on same date.

Regards,

Satish

0