Hi

We have a scenario in which we have a Sales order (Single line) and then we upload the real components in to the Network created by the Sales Order. We do delivery of the Items uploaded in the Network via CNS0. Then the billing is on the Sales order.

What is the recommendation based on IFRS 15 for this scenario?

Will the POB be manually fulfilled when the delivery happens or how does the network delivery get reflected into RAR?

Thanks in Advance,

Vijay V

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member214674
Contributor
0 Kudos

Hi Vijay, RAR reads PGI from sales order. However, if your billing is delivery based then you can use billing to fulfill the POB unless cost recognition is also considered into RAR.

vijaymanikandan
Contributor
0 Kudos

Hi Abhinay

I am looking at Scenario where the delivery happens on a Network / Project. There is no fulfillment event today for this type of delivery happening on Network. Please correct me if I am wrong.