Hi Gurus

I have gone thro the available threads to understand this and got some idea but need to know how can we run this change run in actual system?

Is there some transaction? ( assuming I am not including it in any process chain).

and if i include it in any process chain then after which event do I need to include it?

Pl help.

Thanks

KK

Accepted Solutions (1)

Accepted Solutions (1)

former_member182599
Active Participant
0 Kudos

You could also use RSATTR ..

SID

Former Member
0 Kudos

Thanks Bhanu and siddharth

Points given

KK

Answers (2)

Answers (2)

Former Member
0 Kudos

If you want to include it in process chain - select "Attribute change run" (under - 'Other BW Processes') and select the objects for the process variant

Hope it helps

former_member188975
Active Contributor
0 Kudos

Hi Krishna,

You can run the Attr Change run from RSA1 > menu Tools > Apply Attribute/Hierarchy change. From here you can run immediately or can also schedule as a job.

If you are including it in a process chain, it would be after the load processes that load attr and hierarchies. In the variant of this process you would then maintain a list of the InfoObjects whose attr and hierarchy you want to activate.

Hope this helps...