Enter start and end date in IW41

Hi all

I want to enter start and end time &date in IW41 and that the actual time will be calculated automatically and will be seen in the cost report of the order.

But I only see it of I enter actual work

What am I doing wrong?

Thanks

Irit

dy2bi.jpeg (37.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • Mar 15, 2017 at 12:51 PM

    Irit,

    The Actual Start/End Dates/Times are derived from the individual confirmations.

    This information is then summarised into the order header:

    This data is then visible in IW38/9.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 16, 2017 at 07:59 AM

    Thanks Peter

    Sorry, I still don't understand where do I enter start and end time & date in IW41 instead of actual work and that SAP will calculate the actual work (if it's even possible)

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 16, 2017 at 09:42 AM

    The work start and work end are used to calculate the actual start/end dates/times.

    Have a look at the CONFPM* user-exits to see if the actual work from the actual start/end dates/times.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 16, 2017 at 12:54 PM

    OK I will

    Thanks

    So again, I understand from your answer that in order for the sap to calculate automatically the actual work from the start and end tome and date I must use developer

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 16, 2017 at 05:02 PM

    As far as I know, yes you will need a developer.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 23, 2017 at 07:15 AM

    OK we will check it

    Thanks alot

    Add comment