While doing GRN Actual cost not updating in CJI3

Mar 15, 2017 at 06:42 AM

31

avatar image

Hi,

I have a issue on we are doing GRN movement type is (101). But actual costs are not updating in Tcode CJI3. After that we are doing Goods issue then that costs are update in CJI3.

Why it is not updating actual while doing GRN.

Please suggest on this.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Yuri Orlov Mar 15, 2017 at 06:23 PM
0

Hello,

while doing grn u can update statistical actual cost (type 11) for stock materials. You need to create a cost element with cat. 90 for your account for that scenario.