Skip to Content
avatar image
Former Member

Can finished good possible to run mrp (md02) against bom explosion without demand

Dear all,

Here is my scenario on PP MRP.

"Can finished good possible to run mrp (md02) against bom explosion without demand"?

Is there any configuration for this scenario.

Thanks.

Kelvin.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Mar 19, 2017 at 04:17 PM

    Hello

    If you want to run MRP without a demand, you must define a reorder point MRP type. Another alternative is to use a safety stock for you material, which will act as a demand.


    Regards,
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 19, 2017 at 10:35 AM

    Hello Kelvin,

    Without requirement system will not plan FG goods.

    However, why you want to run MRP (MD02) if requirement is not exist.

    Thanks and Regards,

    Sandeep

    Add comment
    10|10000 characters needed characters exceeded