Aug 02, 2006 at 06:04 AM

Partial confirmation of production order

2165 Views

Hi,

My requirement is that when i partially confirm production order system should calculate the activity time(machine time) propotionately based on actual confirmed qty.

What is actually happening is that system is proposing the machine time based on full operation qty.

I will explain the case with following example:

Total Order qty - 20

Now when i do CO11N the system proposes full operation qty of 20 & also the machine time 20 hrs(based on data given in routing)

Now i when do partial confirmation of 5 units the machine time proposed is still 20hrs.

This is impacting my costing report( as it should consider 5 hrs instead of 20 hrs)

One more thing i want to clarify is that during confirmation we can change the machine time but requirement is that machine time should be in proportion to the confirmed qty(This is to reduce the confirmation effort)

I hope things are clear to you.

regards,

Mohit Goyal