Hi All,

How to copy a proces chain?

Can anybody give me the navigation to copy a process chain?

Thanks

Regards

Dheepa

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi

if u r working on BI7.0 we the direct option copy in menu,

if u r working on BW3.5

T-code RSPC

Select u chain in planning mode, and give "copy" command in tcode box,

then give target name, after that create a start variant and remove the old start variant and add all the process to newly createe start variant.

Former Member
0 Kudos

Dheepa,

Go to RSPC --> Enter COPY in your transaction bar --> So that it will pop up a window asking you the techname and description.. Just go ahead with that..

Hope it helps..

Regards,

Gattu

Former Member
0 Kudos

If you do not want to type COPY..

You can go to process chain...

hit enter.....

then look for first MENU TAB -


PROCESS CHAIN

Select it and look for option -


COPY....

it will prompt you to enter name and technical name of process hcain...

Former Member
0 Kudos

Hi,

Open the process chain which you need to copy and Type =COPY in command line and enter a pop up window will open here give the new process chain name and description, now save and activate. go out of the screen and come again to RSPC you can see the newly copied process chian.

Regards

Sankar

Former Member
0 Kudos

Hi,

go to RSPC-> open your process chain-> enter "COPY" in the place where you enter your TCodes.

Thanks,

Raj

Former Member
0 Kudos

why do we need to copy process chain?

former_member189638
Active Contributor
0 Kudos

If we want to make some changes to Process Chain but we are not sure whether it will work i.e. doing some R&D on the Process Chain then it is better that we create a copy of process chain and change that rather than changing the actual Process Chain........

Also Copying a Process Chain is far better than creating the entire Process Chain again ;-D

Former Member
0 Kudos

select the process chain which you want to copy, and enter 'COPY' in the transaction code box and hit enter.

Regards