Hi Team,

We have EWM integrated with SAP PP. In the process order, the same component has been added twice with the same quantity. After the GI & GR, Inbound delivery was created but, not completed. The IBD was struck in SMQ2. The reversal was supposed to be done on one line item but, done on other line item of the component.

The problem now is, the IBD in EWM was already completed and have been putaway. So i Believe there will be inconsistency now in stock in ECC/EWM with this which resulted to the queue error. Also we can see that the reversal 262 movement type is done for one qty more than the 261 movement type.

Now what can be done in order to remove the inconsistency.