MIGO

Former Member
0 Kudos

Hi,

I am getting an error in MIGO which says Cost element is not assigned to a value field in PA transfer structure..

Does any one know in which transction i have to maintain this?

5 REPLIES 5

Former Member
0 Kudos

Hi Vamsee,

Please check in KA02 and check if your cost element exists.

cheers,

Prashanth

P.S Please mark helpful answers

0 Kudos

It does exist in KA02.

Former Member
0 Kudos

Hi Vamsee,

<b>PA transfer structure</b>

The PA transfer structure defines what sender quantities and values are to be assigned to which value fields of Profitability Analysis during settlement.

You carry out the assignment in two steps:

1. Divide the debit cost elements into groups, and assign each group to an item in the PA transfer structure (this is called PA transfer structure assignment).

2. Assign each PA transfer structure assignment to a value field of Profitability Analysis. Specify that the settled costs are to be regarded as values (instead of quantities), and state whether they are fixed costs, variable costs, or total costs.

You only need to define a PA transfer structure if you want to settle to Profitability Analysis.

Regards,

Azaz Ali.

0 Kudos

Do i have to maintain the value of Cost element category in Cost element to PA structure Value field?

0 Kudos

Hi,

Go through the link for complete documentation,

http://help.sap.com/saphelp_erp2005/helpdata/en/90/ba7289446711d189420000e829fbbd/frameset.htm

Regards,

Azaz Ali.