Dears

We are into SO costing and the production order is created for a sales order after the sales order cost estimate is marked and released.

We have done GRs for the Production Orders and done TECO/DLV status for the orders.

When I run the KKS1 for variance calculation, the "Target Costs' all are appearing as zero(0).

Am I missing something ?

Please help me this difficult situation.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

PATIL PRASAD Mar 14, 2017 at 06:43 AM
0

Hi,

As per my understanding standard cost estimate should be taken at start of the month,so it is applicable to whole month of production orders.

In your case check sale order cost estimate should be taken before creating production order.

Regards

Prasad

Share
10 |10000 characters needed characters left characters exceeded
nikki saju Mar 14, 2017 at 07:26 AM
0

Sales Order cost estimate is already available at the start. Thanks