Skip to Content
0

SAP PI upgrade to PO 7.5

Mar 12, 2017 at 04:55 PM

145

avatar image

Dear All,

We have a scenario to upgrade our PI 7.4 Dual Stack system to PO 7.5 Java Only system. Please clarify below points.

1. Can we upgrade same box or system i.e. inplace?

2. Is it true that Target Java Only system needs to be on Sybase DB? We are using oracle DB at the moment.

3. We used SFTP/PGP keys for SAP SFTP/PGP adapters and shared with the 3rd party systems. Do we need to regenerate them after the upgrade?

4. Is there any checklist to know what needs to be taken care pre and post upgrade?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Harish Mistri Mar 13, 2017 at 12:57 AM
0

Hi,

1. Can we upgrade same box or system i.e. inplace?

-->> Yes you can upgrade the same box.

2. Is it true that Target Java Only system needs to be on Sybase DB? We are using oracle DB at the moment.

-->> As per PAM Oracle DB is supported till 07/2018. Please refer the PAM

https://apps.support.sap.com/sap(bD1lbiZjPTAwMQ==)/support/pam/pam.html?smpsrv=https%3a%2f%2fwebsmp104.sap-ag.de#ts=12&s=&o=most_viewed%7Cdesc&st=l&rpp=20&filter=licensed%7CT&page=1&pvnr=73554900100900000414&pt=t%7CPLTFRM&ainstnr=73554900104900001090&fclfilter=

3. We used SFTP/PGP keys for SAP SFTP/PGP adapters and shared with the 3rd party systems. Do we need to regenerate them after the upgrade?

-->> you can use the same key but it is good to generate new key for new environment.

regards,

Harish