Apo Snp ppm source of supply

Dear Experts

Master data setup

Materal A - plant A

Material B-plant A

Ppm Snp setup

Input mat A

Output mat b

Resource A

Assigned to model 000

Ppm active

Location and mat assigned to model 000

Forcast in material B

Run location heuristics create Snp planned order but source of supply not picking in the planned order

Validity date OK set to past and 9999

Lot size set to 1 to 999999

Still source of supply is not picking

Can someone help me What I am missing

Thanks in advance

Regards

Raj

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 13, 2017 at 01:09 PM

    Hello there forget to assign resource to model all ok now